Cable Erection /Erection of Cable
AIR SPINNING
SQUEEZING
CABLE BAND
CAT WALK ÁöÁöÁ¡ À̵¿
HANGER ROPE °¡¼³
ÁÖÄÉÀ̺íÈ®Àå
HANGER ROPE ÀÎÀÔ
WRAPPING
HAND ROPE°¡¼³
µµÀå
The coil wires weighing about 1 ton for each were carried to the site. The coil wires were placed at the swifter and a wire was drawn out from the coil.

For continuous erection of the cable, the wire was rolled up using a reeler as a larger coil weighing about 5 ton. Shop joints were used for connecting the end of a wire to the beginning of anchor wire. After that, the wire was passed through the counter balance tower to get constant tension. The speed of the spinning wheel was controlled by the driving winch of the hauling system.

At the anchorage, wires drawn out from the counter balance tower were hung on the strand shoe by workmen and then hung on the spinning wheel. Two wires were hung on the spinning wheel.

When the spinning wheel arrived at the opposite anchorage, it was stopped and the wires were taken out from the spinning wheel and hung on the strand shoe. After that, the sag of the wires were adjusted. When 480 wires (1 strand) were erected, they were banded to form a strand. This procedure was repeated to form 14 strands.