Jacking Leg Elevating System |
|
|
|
The part
of the Bridge (L=425M) was divided into 4 blocks
and erected using strand jacks. The applied erection
method can account for the shape change of the truss
during the erection.
The upper chord with high stiffness are used as
the supports of the jacking leg. Therefore, the
lifting frame was not necessary.
Furthermore, the erection unit can be lengthened
so that the number of the field joints can be reduced.
The equipments used during the erection were four
jacking legs (three 600tonf strand jacks/jacking
leg), the skid bearing to be used as the support
during the skidding of the block of the intermediate
support, two 100tonf strand jacks, and so forth.
The erection started with the site assembly of smaller
blocks. The four jacking legs were installed on
the upper chord supports.
Initially, the lifting of 0.5M was conducted for
safety check. After the initial lifting (5.06M),
the block of the intermediate support was skidded
to the top of the pier. Then, the rest of the truss
was lifted 13.6m and the large block and the small
block was connected by splicing all the members.
The connected large block was moved using four 250tonf
hydraulic jacks placed on the bottom of the jacking
leg. |
|
| |
|
|
|
|
|
|
|
| |
|
 |
|
|