The deep foundation was
employed because the site for the Bridge has 20M of
the deposit layer and the bearing layer is generally
located at the depth of 36-40M. For the riverbed, the
well foundation method was applied. For the riverside,
the cast-in-place concrete pile foundation and the steel
pipe pile foundation were used.
|